Gantt chart for activities and sub-activities (Work plan)

Gantt chart for activities and sub-activities (Work plan)

The Gantt chart is a premium feature: it is reserved for the LogAlto Configured and LogAlto+ plans

If you are currently using the Free trial or LogAlto complete plan and wish to get access to Premium features, please contact us at info@logalto.com

  1. Edit the Gantt chart via the activity dashboard
  2. View the Gantt chart of one project (all activities)

Edit the Gantt chart via the activity dashboard

To edit the Gantt chart:

  • Access the activity dashboard:
    • Open the project dashboard.
    • Click on the Activities tab in the project menu and then click on an activity OR Click an activity directly from the "Favorite activities" section of the project dashboard. 
  • The activity dashboard will be displayed and you will see a "Work plan" section.
  • Click the pen icon (In the "Work plan" section, on the right).

  • Select either "Actual dates" or "Planned dates".
  • Enter 1 or many dates interval(s) (start and end dates) and click "Save". Please note:
    • Activities: Start and end dates of activities must be within the project's start and end dates.
    • Sub-activities: Start and end dates of sub-activities must be within the activity's start and end dates.


View the Gantt chart of one project (all activities)

To view the Gantt chart of one project (all activities):

  • Access the project dashboard.
  • Click on the Activities tab in the project menu.
  • Click on the "Chart" option.

  • If needed, select a year from the drop-down list. (The current year is selected by default)