Activities in Documents
This feature is only available for LogAlto+ plans.
If you are currently using another plan and wish to get access to Premium features, please get in touch with us at support@logalto.com
In Logalto, Documents allow users to collect data in a predetermined format and workflow. This can include narrative text, indicator values, activity milestones, and custom forms.
Documents are always associated with a project and for a specific period. If you want more info on document frequencies, please review the article.
Activities in document
In a document, under the Activities tab, you will get a list of activities with the following information:
- Code and name of the activity
- The target of activity for the document period, if any (and depending on the tracking option used)
- Dropdown list to select milestones, if any
- Completion rate
- A dropdown list of status
- Notes field
The flow between activities in the Document module and Project module
The values imported in the Document module and updated in the Projects module follow these events :
- 1
-
The document is created as a
Draft. Activities, sub-activities and milestones statuses and values prior to end of the
reported period are imported from the activity sub-module.
- 2
- Activity statuses and values are updated by users in the document. Values of activities in the associated Project remain the same.
-
-
- 3
- Milestones gets Approved. Activities, sub-activities, milestones statuses, and values for the reported period are updated in the Project for that specific reporting period.
-
-
- 4
-
Document gets
Approved. Activities, sub-activities, milestones statuses, and values for the reported period are updated in the Project for that specific reporting period.
- 5
-
Document goes from Approved to
Draft status. Activities, sub-activities, milestones statuses, and values for the reported period are updated in the Document from what is contained in Project module for the specific reporting period.
Note: If your workflow has multiple approval steps, the final approval is the one that will update the information to your projects.